Client was completing construction of a new metal recycling facility. He failed to recognize the required lead-time to order a supply and exhaust system, which was necessary to ventilate the facility.

A&S was awarded a contract to fabricate and install the supply and exhaust system from flow sheet drawings. To meet the client's schedule the air handling units were fabricated in A&S's shop. Both the client's schedule and budget were met.